10 February 2026
City Centre
Projects reviewed following allocation of funding
On 5 February, Bristol City Council’s Transport & Connectivity Committee reviewed its City Region Sustainable Transport Settlement (CRSTS) programme, after the amounts allocated across the region were confirmed by the West of England Mayoral Combined Authority.
Construction Update
Lower part of Whiteladies Road to fully close for flood prevention works
Whiteladies Road (lower section)
Wednesday 11 to Wednesday 18 February 2026
2 February 2026
Bus Route 2
Proposed changes to multi-million pound transport projects to be considered
Bus Route 2 and Broadmead are two of six major projects, designed to improve sustainable transport options across the city, that are set to be reviewed by Bristol City Council’s Transport and Connectivity Committee when they meet on Thursday 5 February 2026.
9 January 2026
Bus Route 2
Whiteladies Road project extended into the new year
Construction work, to prevent water from pooling and to improve walking, wheeling and cycling routes on the lower part of Whiteladies Road, has started up again after onsite investigations into underground drainage issues were completed.
7 January 2026
A4 Portway
Portway Park & Ride bus entrance to close for new gates to be installed
The final phase of a project to upgrade Portway Park & Ride’s bus entrance, to allow buses from the northwest of the city and beyond to access the Park & Ride site, is taking place this month.
Construction Update
Temple Way works update January to March
Temple Way and its junction with Temple Back East
January to March 2026